Levelling or leveling (American English; see spelling differences) is a branch of surveying, the object of which is to establish or verify or measure the height of specified points relative to a datum. It is widely used in geodesy and cartography to measure vertical position with respect to a vertical datum, and in construction to measure height differences of construction artifacts. In photolithography, the same term is used in a lithography machine calibration step measuring or calibrating wafer surface height with respect to a reference.
The complete unit is normally mounted on a tripod, and the telescope can freely rotate 360° in a horizontal plane. The surveyor adjusts the instrument's level by coarse adjustment of the tripod legs and fine adjustment using three precision levelling screws on the instrument to make the rotational plane horizontal. The surveyor does this with the use of a bull's eye level built into the instrument mount.
A typical procedure for a linear track of levels from a known datum is as follows. Set up the instrument within of a point of known or assumed elevation. A rod or staff is held vertical on that point and the instrument is used manually or automatically to read the rod scale. This gives the height of the instrument above the starting (backsight) point and allows the height of the instrument (H.I.) above the datum to be computed. The rod is then held on an unknown point and a reading is taken in the same manner, allowing the elevation of the new (foresight) point to be computed. The difference between these two readings equals the change in elevation, which is why this method is also called differential levelling. The procedure is repeated until the destination point is reached. It is usual practice to perform either a complete loop back to the starting point or else close the traverse on a second point whose elevation is already known. The closure check guards against blunders in the operation, and allows residual error to be distributed in the most likely manner among the stations.
Some instruments provide three crosshairs which allow Stadia mark measurement of the foresight and backsight distances. These also allow use of the average of the three readings (3-wire leveling) as a check against blunders and for averaging out the error of interpolation between marks on the rod scale.
The two main types of levelling are single-levelling as already described, and double-levelling (double-rodding). In double-levelling, a surveyor takes two foresights and two backsights and makes sure the difference between the foresights and the difference between the backsights are equal, thereby reducing the amount of error. Double-levelling costs twice as much as single-levelling. See: Geodesy .
To "turn" the level, one must first take a reading and record the elevation of the point the rod is located on. While the rod is being kept in exactly the same location, the level is moved to a new location where the rod is still visible. A reading is taken from the new location of the level and the height difference is used to find the new elevation of the level gun. This is repeated until the series of measurements is completed.
The level must be horizontal to get a valid measurement. Because of this, if the horizontal crosshair of the instrument is lower than the base of the rod, the surveyor will not be able to sight the rod and get a reading. The rod can usually be raised up to 25 feet high, allowing the level to be set much higher than the base of the rod.
Ex: an instrument at Point A reading to a rod at Point B a zenith angle of < 88°15'22" (degrees, minutes, seconds of arc) and a slope distance of 305.50 feet not factoring rod or instrument height would be calculated thus:
meaning an elevation change of approximately 9.30 feet in elevation between Points A and B. So if Point A is at 1,000 feet of elevation, then Point B would be at approximately 1,009.30 feet of elevation, as the reference line (0°) for zenith angles is straight up going clockwise one complete revolution, and so an angle reading of less than 90 degrees (horizontal or flat) would be looking uphill and not down (and opposite for angles greater than 90 degrees), and so would gain elevation.
where R is the radius of the earth.
The line of sight is horizontal at the instrument, but is not a straight line because of atmospheric refraction. The change of air density with elevation causes the line of sight to bend toward the earth.
The combined correction for refraction and curvature is approximately:Davis, Foote, and Kelly, Surveying Theory and Practice, 1966 p. 152
For precise work these effects need to be calculated and corrections applied. For most work it is sufficient to keep the foresight and backsight distances approximately equal so that the refraction and curvature effects cancel out. Refraction is generally the greatest source of error in leveling. For short level lines the effects of temperature and pressure are generally insignificant, but the effect of the temperature gradient dT / dh can lead to errors. See: Geodesy .
around a loop. In the real gravity field of the Earth, this happens only approximately; on small loops typical of engineering projects, the loop closure is negligible, but on larger loops covering regions or continents it is not.
Instead of height differences, geopotential differences do close around loops:
where stands for gravity at the leveling interval i. For precise leveling networks on a national scale, the latter formula should always be used.
should be used in all computations, producing geopotential values for the benchmarks of the network.
High precision levelling, especially when conducted over long distances as used for the establishment and maintenance of , is called geodetic levelling.
Precise level designs were often used for large leveling projects where utmost accuracy was required. They differ from other levels in having a very precise spirit level tube and a micrometer adjustment to raise or lower the line of sight so that the crosshair can be made to coincide with a line on the rod scale and no interpolation is required.
The surveyor sets the instrument up quickly and does not have to re-level it carefully each time they sight on a rod on another point. It also reduces the effect of minor settling of the tripod to the actual amount of motion instead of leveraging the tilt over the sight distance. Because the level of the instrument only needs to be adjusted once per setup, the surveyor can quickly and easily read as many side-shots as necessary between turns. Three level screws are used to level the instrument, as opposed to the four screws historically found in dumpy levels.
The sensor can be mounted on earth-moving machinery to allow automated grading.
|
|